|
Stream G: Managing Environmental Projects
|
| Download Stream
G | PDF
| Back
to Stream Index
|
|
| Environmental Remediation
Projects, Common Elements for Successful Clean Up
|
| more |
Steven Rose, MALROZ Engineering Inc.
Rick McGregor, Vertex Environmental Inc.
Experience with numerous contaminated sites has demonstrated the
effectiveness of a fundamental system for employing the basic elements
of environmental remediation. These components of site remediation
have been known and understood for many years, but are often not
followed, resulting in numerous projects that do not meet their
remediation objectives.
Successful remediation depends first on
adequate delineation of the site, characterizing both the extent
of contamination as well
as the structural and hydrogeologic features of the subsurface.
Where possible, the history of contaminant occurrence needs to
be evaluated to gain an understanding of contaminant mass loading
and transport. Once these preliminary data are gathered for a
particular site and contaminant occurrence, the remediation program
can be
appropriately designed for optimum effect.
Following site and
contaminant characterization, the remediation manager’s objective
is to undertake the most efficient program of removing the greatest
mass of contaminant with the least expense
and effort. A flow chart has been developed to illustrate the
prioritization and sequencing of remediation activities. This flow
chart can be
used by remediation managers to guide them through the sequencing
of primary and secondary source removal; removal/degradation/fixation
of dissolved phase contaminants; and, meeting compliance criteria
for the site. T
|
|
| INAC’s Revised
Abandoned Military Site Remediation Protocol
|
| more |
Andrew Liddiard1, Ken Reimer2, Tanya Schulz3, Daniela
Loock2, Bill Horne4, Michael Nahir1, Natalie Plato1
1Indian and Northern Affairs Canada
2Royal Military College
3Golder Associates Ltd.
4EBA Engineering Consultants
In March 2009 Indian and Northern Affairs Canada (INAC) finalized
a revised protocol for the assessment and remediation of the abandoned
military sites under its jurisdiction in the north. The Abandoned
Military Site Remediation Protocol represents a significant update
to INAC’s previous approach for these sites. To develop the
protocol INAC convened a Working Group to collaboratively review
the current state of practice. The resulting document blends aspects
of the Department of National Defence’s DEW Line Cleanup
protocol with the latest state-of-the-art knowledge on contaminants
in arctic ecosystems and climate change. This paper will highlight
the scientific approaches taken in developing key elements of the
protocol. The discussion will also present the quality assurance
approach INAC intends to take in monitoring the implementation
of the protocol as part of the program’s commitment to continual
improvement.
|
|
| Drivers for Site Remediation
Illustrated by Examples
|
| more |
Walter van Veen1, Alan Van Norman1, Devin Doane1, Gary
Campbell2
1Conestoga
Rovers & Associates
2Nova Scotia Lands
The remediation of environmentally impacted sites is driven by
unacceptable risks to human and ecological receptors and involves
removing the sources of contamination and/or severing the exposure
pathways that lead to unacceptable risk. However remediation programs
on their own do not necessarily lead to properties that are amenable
to future use. Remediation and future site use plans are best developed
concurrently, in a symbiotic relationship in which both benefit
from the drivers of the other. The development of future site use
plans are influenced by the following factors:
-
Future needs and planning of the property owner;
-
Relationship between responsible party and property owner;
-
The needs of the community and local government’s planning
strategies;
-
The technical restrictions for remediation; and,
-
Finances available for remediation and development.
The presentation
will examine the site background and the remediation programs
for five sites to identify the drivers for the remediation
and future site use. The sites include the Love Canal in New
York, the Willow Run Creek site in Michigan, a Former Manufactured
Gas
Plant site in Minnesota, the Centre Point site in Michigan
and SYSCO Steel Plant Property in Nova Scotia.
|
|
| Making Risk Based Decisions
to Address Federal Liabilities Related to Contaminated Sites
in the Northwest Territories
|
| more |
Julie Ward, Indian and Northern Affairs Canada
In the Northwest Territories, Indian and Northern Affairs Canada
has an approximate environmental liability of 600 million. The
liability is the sum of the likely costs for remediating all known
contaminated sites that are under federal responsibility. At these
sites remedial methods are selected by using a risk-based decision
process. For example, the remediation of Port Radium focused on
reducing and in some cases eliminating physical and environmental
risks. Physical risks consisted of public access to dilapidated
infrastructure such as buildings and a headframe, and unmaintained
heavy equipment; potential falls into open shafts or unstable crown
pillars; and, access to unmaintained open adits. All physical risks
were eliminated by the removal of infrastructure and equipment,
capping shafts, backfilling or fencing crown pillars, and backfilling
adits. Environmental risks consisted of ecological or human exposure
to uranium rich tailings and contaminated water which pooled on
top of the tailings and waste rock, exposure to the gamma associated
with the waste rock and tailings, and exposure to asbestos particles
associated with the former buildings which were burnt on site and
remaining infrastructure building materials. Environmental risks
were reduced through capping and engineered drainage improvements
of tailings areas, capping of elevated gamma waste rock areas,
and asbestos removal. Contaminant transport offsite consisted mainly
of site drainage through the waste rock and tailings areas. These
risks to the nearby environment were reduced through engineered
capping of shoreline tailings area and drainage improvements throughout
the site. The complete remediation and liability reduction at Port
Radium was $6.8 million. Remediation at other sites resulted in
a similar change in physical and environmental risk and liability
reduction.
|
|
| Project Closure Procedure
for Site Remediation and Risk Management Projects
|
| more |
Eric Wilson1, Gino Dalla Coletta1, Octavio Melo2
1CLAW Environmental Services Inc., in association with Golder Associates
Ltd.
2Indian and Northern Affairs Canada
Indian and Northern Affairs Canada (INAC) manages the environmental
remediation and risk management of a large number of contaminated
sites, located in the Canadian North, that are funded under the
Federal Contaminated Sites Action Plan (FCSAP). As the remediation
of several of the sites under its management was nearing completion,
it was recognised that a procedure for Contaminated Site Remediation
Project Closure needed to be developed for INAC’s use. Realising
that a process for project closure has already been developed by
Public Works and Government Services Canada on behalf of FCSAP
as part of the overall project management tool set for contaminated
sites, INAC and CLAW/Golder Associates Ltd. set out to apply this
procedure and adapt it as necessary to suit the needs of the department.
Based on discussions with stakeholders within the department,
it was apparent that project closure documentation would have to
focus
on two distinct audiences, one comprised of external stakeholders
such as the local community, aboriginal groups and licensing
boards, and the other comprised of internal stakeholders including
INAC
and the Treasury Board of Canada, Secretariat.
The procedure focuses
on the creation of a Project Closure Report that meets the needs
of both sets of stakeholders. The aim of
this Project Closure Report is to document the history of the
remediation
project that was undertaken and completed at a site by describing
what was planned, what was actually completed at the site and
what remains outstanding. The Closure Report focuses on remediation
activities completed under the FCSAP program. It provides a ‘snap
shot’ of the physical condition of the site at the time
this report is produced (i.e., the end of the project).
The
Closure Report also outlines the on-going monitoring and/or
maintenance requirements for the site that need to be carried
out after the remediation project is completed. It identifies
internal
INAC divisions or branches and/or external organisations
that are intended to assume responsibility for these on-going requirements.
It also clearly identifies permanent site features such as
tailings caps or solid waste landfills that will remain on
the site post-remediation
that will require protection in the future in order to safeguard
the Crown’s investment.
Finally, another aim of the
Project Closure Report is to evaluate the overall performance
of the project at a high
level such
that best practices and lessons learned can be identified,
documented
and ultimately put in practice by the organization on other
projects.
|
|
| Document Management in
the 21st Century
|
| more |
Devin Doane, Donna Steele, Hilary Fitzgerald, Walter van
Veen
Conestoga-Rovers & Associates
The role of the Independent Engineer (IE) for the Sydney Tar Ponds
Cleanup is generally to protect the interests of the federal government
and Nova Scotia provincial government as well as the people of
Canada and Nova Scotia, by performing third party due diligence
with respect to health and safety, quality, financial, and schedule
for the Tar Ponds and Coke Ovens Remediation Project (Project).
This role requires the exchange of thousands of emails, letters,
and reports. To date, half way through the Project the Independent
Engineer has on file approximately 10,000 records. This number
should more than double by the end of the Project.
To maximize
the efficiency of the IE review role through the life of the
Project, the IE has developed systems of libraries and databases
to manage the exchange of correspondence (such as letters, e-mails,
and memorandums) and documents (such as design reports, tender
documents, and RFP’s). Furthermore, the IE maintains a
detailed “Comment
Database” which enables them to track the status (open,
closed, deferred) of individual Independent Engineer questions
and responses
to these questions that the Independent Engineer generates as
part of its ongoing role. This database contains over 3,000 comments
with the associated responses. A third database tracks the Independent
Engineer’s observations of construction activities. As
well, customized spreadsheets facilitate effective change management
tracking, enabling contract managers a direct link to change
order
documents and current contract commitment information. Tracking
project data in electronic format requires foresight and planning
but can save much time and money through the life of a Project.
The
presentation will review the evolution of document management – from
filing cabinets to detailed spreadsheets and relational databases,
with emphasis on a description of the IE tools used.
|
|
| Project Planning and
Quarterly Progress Reporting Against Plan
|
| more |
Octavio Melo, P. Eng., Indian and Northern Affairs Canada
Indian and Northern Affairs Canada (INAC) manages the environmental
remediation and risk management of a large number of contaminated
sites, located in the Canadian North, that are funded under the
Federal Contaminated Sites Action Plan (FCSAP). As FCSAP was approved
in 2005 and INAC’s Northern Contaminated Sites Program (NCSP)
was expanded, more formal project management processes were introduced
to enhance and standardize the planning and execution of projects.
Two of these processes involve the development of project detailed
work plans and quarterly reporting against plan.
An initial detailed
work plan (DWP) is prepared for newly approved projects that
are estimated to cost over $250K (i.e., most of NCSP’s
projects). The DWP documents the site issues to be addressed
by the project, and then sets out to describe the objectives, scope,
risks, plan, team, delivery strategy, controls, schedule and
resource
requirements for the project. The plan is peer reviewed before
being finalized and approved by Senior Management. Once approved,
the DWP becomes both a plan for executing the project and a project
charter between the Project Manager and NCSP Management. The
DWP is updated annually (or more frequently if planning assumptions
change significantly during the year). The annual update provides
an opportunity: to add more detailed information on risk, plan,
cost, schedule, etc. that may have become available (i.e., as
the
project progresses from remediation strategy development to design,
procurement and implementation); to reconcile plan vs. actual
achievements for the previous year; and, to document lessons learned.
Quarterly Reports (QRs) are produced to document and communicate
progress during the quarter. QRs track the progress of the
work, using a standardized work breakdown structure, against planned
schedule and cost. The reports also document performance against
a number of performance indicators (i.e., environment, health
and safety, socio-economic benefits, stakeholder engagement).
An executive
summary allows the Project Manager to summarize, at a high
level:
the progress being made; any deviations from plan and the reasons
and measures planned to address these deviations; and, any
significant concerns that threaten the achievement of project objectives.
QRs are addressed to and for the information of NCSP management;
a
high-level summary (i.e., dashboard) is prepared at the program
level to facilitate review and action by management.
|
|
| Innovative Uses of GIS
as a Project Management Tool
|
| more |
Belinda Campbell, Public Works and Government Services Canada
Public Works and Government Services Canada (PWGSC) Atlantic has
been developing innovative ways of using web-based GIS management
tools since 1994. From major crown construct projects, to complex
remediation programs and nation-wide business programs, web-based
GIS software has provided PWGSC with an efficient and remote access
based system that provides a single, secure, audit ready, repository
of geographic and textual data with direct remote population, query,
analysis, reporting and dissemination capabilities. The innovated
use of this application with other off the shelf applications has
enabled multiple levels of government and private industry to exchange
information quickly and efficiently in a safe and secure web-based
environment using Autodesk MapGuide, ESRI ARcServer, SQL Enterprise
and Oracle database technologies. Linked with other software such
as MS Share Point, PWGSC has managed projects of complexity such
as the Confederation Bridge construction project, remediation projects
such as the Sydney Tar Ponds and Coke Ovens Project, DEVCO mine
closure and Argentia naval base closure, to the national business
structure of the Accelerated Infrastructure Program. The approach
provides an ongoing project management tool in spatial organization
and presentation that is efficient and easy for multi-level usage.
|
|
| Enabling Remedial Solutions
through Innovative Procurement
|
| more |
Michael Billowits, Quantum Murray LP
Harold Brillinger, Public Works and Government Services Canada
Lynn Warner, Transport Canada
Quantum Murray LP was awarded a contract by Public Works and Government
Services Canada (PWGSC) on behalf of Transport Canada in October
2008 to remediate a five hectare surplus seaway property in St.
Catharines with approximately 26,000 tonnes of near surface soil
impacted by hazardous concentrations of lead as well as polycyclic
aromatic hydrocarbons (PAHs) deriving from the historical operations
of a skeet shooting range. The surplus property is to be divested
for redevelopment purposes. Procurement used a Request for Proposal
with evaluation criteria that was utilized by PWGSC and Transport
Canada to choose the remediation approach from the environmental
contracting community and to maximize the benefits of the treatment
methods available. Details of the stabilization remediation approach
utilized at the St. Catharines project will be provided along with
a description of how Quantum’s remedial solution proposed
a 35% savings while also satisfying the schedule requirements and
stakeholder objectives for the tendered project scope.
|
|
| Putting the VALUE in
Value for Money
|
| more |
Alan Van Norman1, Walter van Veen1, Brandon Hurl1, Mike
Nahir2
1Conestoga-Rovers & Associates
2Indian and Northern Affairs Canada
An underlying objective of government spending is often described
as the desire to receive value for money. Value is difficult to
measure and is frequently a matter of perception. Value does not
have a unique metric that can be measured and reported. There are
at least two major components of value that are related to government
spending. The first opportunity to create value is strategic. Strategic
value arises from the selection of projects that get funding and
their order of priority. Strategic value reflects the implementation
of government policy. The second opportunity to create value for
money comes at the implementation stage. Implementation value is
created by ensuring that the funded project is efficiently completed.
As managers and overseers of funded projects it is our collective
responsibility to ensure that implementation value is realized.
This paper will focus on achieving implementation value.
Implementation
value for an environmental remediation project is a function
of cost, schedule, and quality of the end product. When
a scope of work is defined and the desired quality is specified
the schedule and cost can be calculated. In most cases the specified
quality with the calculated cost and schedule defines the balance
between these inputs with the highest implementation value for
a given scope of work. In a few special cases budget and or schedule
may be fixed and quality must be adjusted to achieve the desired
implementation value. In every case, quality is the key input
to defining and demonstrating implementation value and in most
cases
quality is the value input function that does not receive the
appropriate level of attention from implementers. This paper will
define the
importance of quality in achieving value for money and describe
how quality measurement and reporting can be built into an environmental
remedial action at the program level and at the design, specification
and construction implementation level. The role of quality in
support of the principle of transparent accountability will also
be discussed.
Measurement and reporting of value for money will be supported
with examples.
|
|
| Getting on the Same Page:
A Practical Tool for Inter-Agency Collaboration in Risk Communication
|
| more |
Ronald W. Brecher, GLOBALTOX International
Consultants Inc.
Trevor Smith Diggins, www.smithdiggins.com
Government agencies often face the difficult task of communicating
risk-based information to concerned stakeholders. As public awareness
of environmental risk increases, so does the need for effective
risk communication. Establishing and building credibility is critical
to ensure successful communication with a concerned public.
Risk
communication can be significantly more challenging when two
or more departments within an organization (for example, the Government
of Canada) are jointly involved in responding to stakeholder
concerns.
Involved departments or programs are often responsible only for
limited aspects of an issue, or differ in their priorities, goals,
policies or precedents. Therefore, responses must be co-ordinated
in order to avoid inconsistent messages being delivered to external
stakeholders. A successful multi-agency risk communication program
will reduce the likelihood of stakeholder confusion and project
delays, and promote credibility for the process and the organizations
involved.
This paper describes a simple tool and process that
multi-agency groups can use to identify their stakeholders’ concerns
and prepare co-ordinated responses. This tool, the Response Matrix,
has been used effectively by the authors to assist clients in
recent
national risk controversies in Canada.
|
|
| Guidance and Orientation
for the Selection of Technologies (GOST)
|
| more |
Jennifer Holdner1, David Juck1, Martin Desilets1, Charles
Greer1
1Biotechnology Research Institute – National Research Council,
Montreal, QC
A new web based tool is available to assist project managers in
selecting potential remediation technologies for their sites. The
Guidance and Orientation for the Selection of Technologies
(GOST) site can provide a list of site and contaminant appropriate technologies
based on user supplied data (Technology Selection Tool), detailed
Fact Sheets covering over 60 remediation technologies and links
to additional resources.
The Technology Selection Tool will provide
a list of technologies appropriate to the specific site based
on a questionnaire completed
by the site manager. Information such as contaminant type, concentration
and depth, hydrogeology, environmental matrix, etc. is entered
and a customized list of appropriate technologies is created.
Details regarding each technology can then be accessed through
individual
Fact Sheets, currently numbering over 60, which provide information
on technology application and limitations, target contaminants,
complementary technologies, analyses required for detailed site
characterization, case studies and references for that technology.
GOST is the Canadian reference tool for project managers involved
in site rehabilitation and remediation, providing invaluable
information on technologies targeting contaminated site cleanup
in Canada.
The online tool was developed for Public Works and Government
Services Canada (PWGSC) by a multi-disciplinary team composed
of experts
from the Biotechnology Research Institute of the National Research
Council of Canada, the Montreal Centre of Excellence in Brownfields
Rehabilitation and the private sector.
|
|
|