|
Stream E: Assessment and Remediation
in Special Environments
|
| Download Stream
E | PDF
| Back
to Stream Index
|
|
| Fox-C Ekalugad Fjord
Lobe B Dump “Excavation”
|
| more |
Mark Yetman, Indian and Northern Affairs Canada
The FOX-C Intermediate Distant Early Warning (DEW) Line Site was
constructed in 1957 and subsequently abandoned in 1963. It is located
on the Northeast coast of Baffin Island, Nunavut on the south shore
of Ekalugad Fjord. It is approximately 240 kilometres northwest
of Qikiqtarjuaq and 260 kilometres south of Clyde River.
At the
conclusion of the 2007 season a thorough review of the remaining
work was completed and it was determined that if site conditions
in 2008 were the same as those encountered in previous years
then the methodology being used to excavate the Lobe B dump would
not
allow for the completion of the work in one extra year. To increase
our chances of completing the remaining work in 2008 a new methodology
would have to be developed.
The original plan for the Lobe B dump
was to excavate and segregate it using heavy equipment. This
was to be completed in steps by
removing the surface materials and scraping down to the frozen
area, allowing it to thaw, and then repeating the process.
The progress made in 2007 projected that the work remaining at
Lobe
B would take around 90 days to complete using this methodology.
Since the typical field season at FOX-C lasts around 60 days
an alternative methodology would be required if we wanted to
increase
the probability of completing the project in 2008.
A number
of alternatives approaches to Lobe B were discussed during off-season
meetings. These options were reviewed and
discussed with consideration given to the site characteristics
and other
factors (limited access, available equipment, cost, permitting,
scheduling). Upon completing the review it was decided that
the use of explosives to loosen the material would give us
the best
opportunity to complete the project in 2008.
The change in
the approach to Lobe B was just to the methodology used to excavate
the material. Once the material is removed
it was to be segregated and handled as described in the
original approach. In order to expedite the excavation process
a certified
explosives
contractor was hired to come to the site and strategically
place
charges to loosen up the material. This allowed us to excavate
the loosened material and move it to the lower site processing
area where it could thaw quickly and be segregated and
properly handled.
The new methodology successfully loosened the
material and it was excavated and moved to either the non-hazardous
waste
landfill
(debris) or the material processing area where it was
placed in
piles and sampled. Confirmatory sampling of Lobe B indicated
that the area was successfully cleaned. The use of explosives
to loosen
a frozen dump proved to be successful methodology.
|
|
| Control, Mitigation,
Assessment, and Remediation of a Significant Hydrocarbon Release
in a Heavily Sloped Discontinuous Permafrost Environment, BAF-3,
Brevoort Island, Nunavut
|
| more |
François Lauzon1, Robert McCullough1, David Wilson1,
Scott Charland2, Kim Kalen3
1Stantec
2The Nasittuq Corporation
3North Warning System Office, Department of National Defence
In March 2007, Stantec was retained by the Nasittuq Corporation
to assist in the emergency response, assessment, and clean-up,
following a 150,000 L Jet A-1 fuel spill that occurred at the summit
of a Department of National Defence (DND) Long Range Radar (LRR)
site (BAF-3); a part of the North Warning System (NWS), on Brevoort
Island, Nunavut. This multi-faceted project included a step-wise
approach to the assessment and remediation in consideration of
the environmental and logistical challenges imposed by weather,
topography, isolation, and discontinuous permafrost.
Prior to initiating
a “traditional arctic Phase II Environmental
Site Assessment (ESA)”, Stantec (formerly under the Jacques
Whitford banner) conducted a preliminary investigation (visual
and olfactory) to delineate the PHC impacts in the surface snow
and ice (the PHC release was complicated by a 40,000 L water
line break on top of the PHC plume). This assessment, completed
by the
end of March 2007, allowed for the development of a control and
mitigation strategy requested by an INAC Order. The plan needed
to address the potential uncontrolled flow of PHC impacts, temporarily
halted in the winter environment, throughout the spring freshet
to mitigate potential flow of free product to the Arctic Ocean.
The plan resulted in the construction of control structures (underflow
dams) and the installation of a water treatment system to treat
approximately one million litres of PHC-impacted water in year
one. During the Phase II/III ESA completed by September 2007,
information was collected to perform a Human Health and Ecological
Risk Assessment
(HHERA). Two hundred and eighty one samples were collected throughout
the Phase II/III ESA. Screening based on soil vapour concentrations,
field observations, and PetroFLAG ™ test kit, resulted
in 86 soil samples submitted for laboratory analysis of Benzene,
Toluene,
Ethylbenzene, Xylenes (BTEX) and Petroleum Hydrocarbon Contaminants
(CWS PHCs – Fractions F1 to F4). Soils were also submitted
to the National Research Council Biotechnology Research Institute
(NRC BRI) to optimize the microbial nutrient approach for sustained
bioremediation on site. The ESA and HHERA, as well as the microcosm
study results from the NRC BRI, allowed the development of a
point-rated remedial options analysis to select the most appropriate
treatment
train approach to deal with multiple media: impacted water, soils,
and waste adsorbent materials (boom and pads). The resulting
Remedial Action Plan (RAP) includes remedial excavation and placement
of
soils in an engineered landfarm (on-site, licensed by a Nunavut
Water Board Application), soil flushing to mobilize PHCs that
are inaccessible due to infrastructure and utilities, continued
operation
of a water treatment system and continued control and mitigation
efforts (2008, 2009, and 2010) to deal with sporadic subsurface
PHC migration (free product) affected by the discontinuous permafrost.
The site is expected to be remediated by the end of the 2010
field season, with continued landfarming and site monitoring
up to 2012.
This paper will outline the step-wise strategic field
approach
developed for this complex site and provide early results from
the biostimulation in the landfarm as well as from the soil
flushing component of the project. It will further outline the
logistical
challenges imposed by the nature of the site (schedule constraints
exacerbated by extreme weather conditions (fog and high winds),
logistical and equipment constraints from working in a remote
location, steep and uneven terrain being assessed, and significant
scrutiny
from stakeholders), and discuss the impacts of the rapid thaw
of the discontinuous permafrost in consideration of “observed” climate
change.
|
|
| Reaching Cam-F, Cam-5
and Fox-3 DEW Line Sites: Challenges and Lessons Learned
|
| more |
Jean Pierre Pelletier1, Sylvain Laberge1, Jared Buchko2,
Kailapi Alorut3, Michel Pouliot1
1Biogénie
S.R.D.C. Inc.
2Public Works and Government Services Canada
3Sila Remediation Inc.
The Distant Early Warning (DEW) Line is a network of 63 radar
stations (42 in Canada) built in the mid-1950s, at the peak of
the Cold War. It took three years of intensive work to the United
States to build this system in the Arctic. It was designed to detect
any aircraft approaching from the North Pole. It was operated jointly
by the Canadian Department of National Defence and the USA Airforce.
The DEW Line was composed of six main sites, 26 auxiliary sites
and 31 intermediate sites.
CAM-F, one of the intermediate sites,
closed in 1963 and was transferred to INAC in 1976, along with
20 other stations. CAM-5 and FOX-3,
both auxiliary sites, closed in the early 1990’s. The stations
were comprised of the following infrastructure: module trains,
garages, warehouses, sheds, communication towers, POL tanks and
storage facilities, etc. Wastes and contaminants present on site
included: PCBs (present in soil, oil and painted material), hydrocarbon
(present in soils), metals present in soils, asbestos, etc.
CAM-F
and CAM-5 are both located on the Melville Peninsula. The closest
communities are Hall Beach and Igloolik, which are located
approximately 100 km from CAM-F and 225 km from CAM-5. FOX-3
is located on Baffin Island, approximately 200 km west of Clyde
River.
All three sites can only be accessed by plane or helicopter
in the summer and via snowmobiles in the winter.
Biogénie
was awarded the CAM-F Cleanup Project contract in 2005, the CAM-5
contract in 2006 and the FOX-3 contract in 2007.
All projects required heavy equipment, material and a construction
camp to be mobilized on each site in order to perform the
remediation work. Winter/over tundra transportation is a challenging
expedition
requiring a specific logistic and knowledge of the area.
This
paper will present some challenges and issues encountered during
the mobilization to each site. Topics such fluctuating
winter conditions, special permit and aboriginal content
requirements will be addressed and discussed.
|
|
Rapid Assessment and
Remediation Approach: Mercury Contamination at Hydrometric
Stations in British Columbia
|
| more |
David Kettlewell1, Rae-Ann Sharp2, Curt Naumann2, Meredith
Guest3
1SNC-Lavalin Environment Inc.
2Public Works and Government Services Canada
3Environment Canada
The Water Survey of Canada (WSC), a branch of Environment Canada
(EC) operates a network of up to 3,000 hydrometric stations across
the country for the purpose of collecting water level and river
flow data. These stations typically consist of a small walk-in
shelter containing monitoring and communication equipment. Between
the early 1970s and the mid-1990s mercury servo-manometers coupled
to chart recorders were used to collect and record data. During
this period, mercury releases from the servo-manometers occurred
nationally at up to 1,300 locations due to freezing of the system
hoses causing mercury overflow and release, spillage during regular
maintenance of the equipment, and/or vandalism.
A national program
to assess and remediate the mercury contamination has been underway
since 1999. In British Columbia, upwards of 70
stations were assessed on a yearly basis in a variety of urban
and remote locations around the province. Project management
challenges that were overcome included obtaining appropriate site
access agreements
from property owners for each of the sites (including First Nations,
federal and provincial owners), gaining access to remote sites
via use of helicopters and off-road vehicles, and establishing
appropriate health and safety guidelines and communication protocols
with the remote field team working extended hours (including
use of a SPOT satellite transponder to track crew position throughout
day and developing emergency response procedures in the event
of
an emergency message sent or missed call-in).
Rapid assessment
and remediation techniques were developed to allow for the quick
identification of potentially impacted areas,
assessment
of impacted materials on-site using portable mercury analytical
equipment (mercury vapour concentrations inside the hydrometric
station shelters and mercury concentrations in soil), remediation
of impacted areas and removal of impacted material off-site,
and confirmation sampling – usually within a single day.
Multiple stage QA/QC procedures were developed to confirm the
correlation
of analytical results obtained from portable field equipment
with results from off-site laboratories. Assessment procedures
were
modified as the project progressed to account for site observations
and individual site characteristics such as sampling and analysis
of high organic content and high moisture content soil and assessing
and remediation of impacted soil on flood plains. Rarely was
mercury contamination observed to extend beyond 15 cm depth,
even when
the contamination was > 20 years old in high precipitation
coarse-grained environments. The mercury appeared to bond to
soil particles strongly
minimizing vertical migration into the subsurface despite its “liquid” metallic
state.
|
|
| Assessment and Remediation
of a Coastal Wetland Ecosystem
|
| more |
G. Michael Charles, Stantec Consulting
Bill Kelly, Maritime Forces Atlantic (MARLANT), Department of National
Defence
In 1999, the Department of National Defence conducted a surface
soil investigation and identified the presence of petroleum hydrocarbon
impacts in the wetland area and along the coastal beach area of
the DCD Fire Training Centre, near Halifax Nova Scotia. The wetland
area is located in the central portion of the DCD school site,
southeast of the former fire fighting training area (FFTA). An
initial remedial program was completed in 2002 using in-situ application
of oxygen releasing material (ORM) to remediate impacted wetland
soil and sediment. However, after several years of monitoring soil/sediment
hydrocarbon residuals, the treatment method was deemed ineffective
and alternative remediation methods were required.
This paper presents
a summary of the unique site conditions associated with this
impacted wetland, management and assessment of complex
issues associated with the wetland and coastal region, and special
requirements for post-clean-up restoration to a fully functional
wetland habitat.
|
|
| Giant Mine Remediation
Project: Environmental Assessment and Regulatory Processes
|
| more |
Lisa Dyer, Public Works and Government Services Canada
Tricia McFaull, Indian and Northern Affairs Canada
The Giant Mine is located in Yellowknife, Northwest Territories,
and produced gold from 1948 until 1999. Gold in the Giant Mine
ore is associated with an arsenic-bearing mineral known as arsenopyrite.
The roasting process used to liberate the gold from the arsenopyrite
led to production of arsenic trioxide dust. Approximately 237,000
tonnes is stored in sealed underground storage areas on the Giant
Mine site. The arsenic trioxide dust is hazardous to both people
and the environment.
After the mine owner went into receivership
in 1999, the mine was transferred to the Department of Indian
and Northern Affairs Canada
(INAC). INAC and its Technical Advisor developed a remediation
plan for Giant Mine. The remediation plan outlines the clean
up of the entire mine site, including the long-term management,
containment
and storage of the arsenic trioxide dust. The remediation plan
was submitted to the Mackenzie Valley Land and Water Board for
regulatory approval in October 2007.
In February 2008, the Mackenzie
Valley Land and Water Board released its decision to not refer
the Giant Mine Remediation Plan to
environmental assessment under the Mackenzie Valley Resource
Management Act and
instead move straight to the permitting process required for
the project. In March 2008, however, the City of Yellowknife,
under
the Mackenzie Valley Resource Management Act, referred the
remediation plan to environmental assessment. INAC is currently
participating
in the environmental assessment for the Giant Mine Remediation
project as the proponent for the project.
This presentation
will provide an overview of the environmental assessment process
for a large-scale remediation project. The
presentation will focus on the steps taken by INAC and Public
Works and Government
Services Canada (PWSGC) to effectively participate in the
environmental assessment while simultaneously completing care and
maintenance
activities on the site. Both the challenges and lessons learned
by INAC and PWGSC will be explored.
|
|
| Faro Mine Complex Remediation
Project: Options and Decision Making for Closure
|
| more |
Michael Nahir, Contaminated Sites Program, Indian and Northern
Affairs Canada
Stephen Mead, Abandoned Mines Program, Government of Yukon
Daryl Hockley, SRK Consulting
The Faro Mine Complex is a very large abandoned lead-zinc mine
in the Yukon Territory, Canada. In 1998, all mining operations
stopped at the Faro Mine Complex after the last owner, Anvil Range
Mining Corporation, was placed into receivership. Due to the nature
and magnitude of the contamination there will be no walk-away solution
to remediating the site. The potential for acid rock drainage is
widespread in the waste rock piles and tailings impoundment. Significant
impact will occur in the fish bearing rivers downstream of the
site if not controlled. The provincial and federal governments
have entered into a joint agreement with the local First Nation
to work together on the development of a closure plan for the Faro
Mine Complex. To ensure support for the preferred closure option,
there was a need to involve a wide range of stakeholders/interested
parties in the assessment.
This paper describes the site closure
objectives, issues and the remediation options to reduce site
liability and risk to human
health and the environment. Other objectives are to reduce impact
to traditional land use and to support socioeconomic activity
for First Nations and Yukoners. A multi-attribute analysis was
developed
and used with stakeholder representatives to assess closure options
against objectives and a cost-benefit analysis was performed
with the results.
|
|
| Colomac Mine Remediation
Project: Project Overview
|
| more |
Ron Breadmore, Tlicho Region, Contaminants and Remediation Directorate,
Indian and Northern Affairs Canada
Colomac Site History and Project Background
Colomac is located 220 km north of Yellowknife with site access
via airlift and winter road. The site is upstream of the Indin
Lake watershed within the traditional lands of the Tlicho people.
The Bathurst caribou herd, which migrates annually through the
area, are critical to the Tlicho not only as a primary food source
but also as an integral part of their spiritual and cultural
identity.
Mineral exploration in the area started in the 1930s
and the mine operated from about 1990 through 1997. The site
was abandoned by
Royal Oak Mines Inc. in April 1999, leaving behind contaminated
tailings, hydrocarbon impacts, open pits and quarries, waste
rock dumps, hazardous materials and mine infrastructure. The most
pressing
issue was the management of contaminated water and, by the end
of 1998, Tailings Lake was threatening to overtop Dam 1. An emergency
amendment granted under Section 39 of the Northwest Territories
Waters Act allowed for the transfer and safe storage of tailings
water to the Zone 2.0 Pit.
Through comprehensive risk characterization
and risk assessment, Indian and Northern Affairs Canada (INAC)
worked closely with
the Tlicho Elders and Executive and developed the Colomac Remediation
Plan in March 2004, which was approved by the Mackenzie Valley
Land and Water Board. Colomac has been undergoing full remediation
since that time.
Site Risks and Mitigations
Tailings and Tailings Water Management
Water management (diversion ditch program), water treatment
(Enhanced Natural Removal program using fertilizer) and
construction of
Dam 1B, tailings cap and spillways within the Tailings
Containment Area (TCA) have effectively mitigated these risks.
Hydrocarbon
Remediation
Full-scale hydrocarbon remediation commenced in 2004 with
decommissioning of the former Tank Farm, soil treatment
and free product recovery.
Enhanced free product recovery, Steeves Lake shoreline
remediation, human health and ecological risk assessment
and post-closure
containment planning are in progress and will form the
Final Hydrocarbon Remedial
Action Plan.
Major Demolition
Select mill equipment has been removed from the mill
for re-use in other gold mining projects and mill decontamination
and
demolition will continue with the removal of residual
tailings
and demolition
of the mill facilities, maintenance shop and camp complex.
All demolition wastes will report to the non-hazardous
waste landfill
and salvaging options will be pursued to the extent
possible.
Site Restoration
A number of stream crossings will need to be restored
across the site as well as the reconstruction of a
fish passage
channel between
Truck Lake and Steeves Lake.
Site Clean up and Non-hazardous
Waste Consolidation
Almost 10,000 tonnes of clean scrap steel, tires
and tailings pipe have been placed in the non-hazardous
landfill (located
in Zone
2.5 Pit) to date. While addressing safety hazards
(loose
rock and residual unexploded ordinances), the site
operator, Tlicho
Logistics,
brought down enough rock to provide a one metre cover
and address the safety hazards at the same time.
Colomac
and the Tlicho Community
Fence Project
The 2008 TCA soil and vegetation survey confirmed
that contaminant levels in the soil and vegetation
were
greatly reduced since
the 2003 survey and are once again safe for the
caribou. The caribou
fence has been since been decommissioned.
Youth
Employment and Apprenticeship Program
One of the Tlicho participants in the 2007 Youth
Science Workshop was hired on as an Assistant
Environmental Technician for the
2008 TCA survey. Tlicho Logistics has successfully
established and maintained
training priorities for Tlicho community members
through
the Colomac Apprenticeship Program and many
of the apprentices have transferred
their skills to operating mines.
Elders’ Support
Tlicho Elders identified the Colomac Mine Site
as a major concern early in the Tlicho Land
Claim negotiation
process
and were
instrumental in the development of the Colomac
Remediation Plan. The Elders
are still very much involved with Colomac
and tour the site twice annually to check on wildlife
issues
and remediation
progress.
Final Demob and Post Closure
Final demob is scheduled for March
2012 and project closure planning has started.
|
|
| Assessment and Remediation
of Petroleum Hydrocarbons in Fractured Bedrock at the Colomac
Mine
|
| more |
Kevin Biggar, Andrew Richardson, and Olu Iwakun
BGC Engineering Inc.
The Colomac mine is currently undergoing significant remedial
work under the oversight of Indian and Northern Affairs Canada.
As part of this effort, fuel tanks have been deconstructed and
the impacted overburden from the tank farm area excavated for treatment
in a biopile. Residual contamination is present in the underlying
bedrock. Remediation of petroleum hydrocarbons in fractured bedrock
is a difficult challenge in temperate climates, and is more complicated
by the presence of permafrost and deep seasonal freezing and thawing.
To
better understand the flow field and groundwater geochemistry
detailed sampling and testing has been conducted since 2005 including:
- Water level measurements in approximately 35 monitoring wells;
- Water samples to measure inorganic and organic chemical
concentrations as the active layer thawed and the water depth changed;
-
Periodic bail tests to determine free product recovery in select
wells;
- Packer tests conducted over intervals to obtain hydraulic
conductivity versus depth profiles; and,
- Installation of thermistor cables and data loggers
in a number of boreholes to determine the thermal
regime at the site.
Remedial activities have also
been undertaken including
removal of free product from existing monitoring
wells, excavation
of a large trench in one of the most heavily contaminated
areas for
free product collection, and applying vacuums to
some wells to
enhance product recovery.
The active layer depth in
the monitoring wells was highly variable, with thaw depths in
excess of 20
m measured
in some wells.
There also exists a talik beneath a heated warehouse.
Hydraulic conductivities
in the bedrock ranged from 3 x 10–5 m/s
to being too tight to measure at depths greater
than approximately
4.5 m in
some wells,
but not
others. Median values were approximately 4x10–6 m/s.
Total dissolved solids in the groundwater ranged
from 100-1200 mg/L, with an average value of
600 mg/L. The
groundwater
is dominated by calcium, sulphate, and bicarbonate,
with minor
amounts of
sodium, potassium, iron, manganese, and small
amounts of chloride. The
iron and manganese were obtained from field filtered
and acidified samples, and indicate a reducing
environment even up gradient
of the contamination, which was surprising given
the shallow
nature
of the site. Dissolved hydrocarbons were found
in all wells sampled but one. However, many of
the wells
had
contained
free product,
so concentrations obtained from these wells are
questionable. In wells with no free product in
2005, CCME F1 fractions
(n-C6 to
n-C10) varied from 30 ug/L to a high of approximately
3500 ug/L, with a median value of approximately
400 ug/L. These
geochemical
indicators suggest that intrinsic bioremediation
is ongoing.
Free product recovery in the fractured
bedrock was very difficult. Despite thicknesses in some
wells
of metres
of free product
in the winter when the water table was at its
lowest, recovery of
free product after initial product removal
was very slow. A large trench blasted and excavated
into the
bedrock
in the
most contaminated
area had more success, however was very costly.
Vacuum application to monitoring wells to enhance
free product
recovery was
met with limited success.
|
|
| 5 Wing Goose Bay Remediation
Project
|
| more |
Craig Wells and Susan Drover
Department of National Defence
The Department of National Defence (DND) is currently managing
over 100 suspected and confirmed contaminated areas at 5 Wing Goose
Bay (located in central Labrador) and is developing a comprehensive
remediation plan that will reduce or eliminate the potential risks
posed by the contamination.
Environmental contamination at the Wing
can be attributed to several sources. Major hydrocarbon plumes
can be attributed to leaking
underground and aboveground storage tanks, leaking or ruptured
pipelines, and historical management and containment practices.
Heavy metals and other chemical contamination (i.e., PCBs, VOCs)
are due to historical waste disposal practices and the existence
of numerous dumpsites.
5 Wing Goose Bay is considered a remote
site, due to the limited ways of getting to the area. The Wing
itself covers over 5,400
hectares, access to which is mostly unrestricted, and approximately
20% of which is comprised of wetlands. This creates a considerable
habitat for aquatic and terrestrial receptors, along with human
receptors from people working on the Wing and those who use
the land for recreational purposes.
The challenge will be to plan
and execute the remediation project in such a way as to minimize
disturbance to the various impacted
areas, while remediating or risk managing the contamination
in accordance with Government of Canada policies related
to the
management of contaminated sites.
DND is taking a holistic
management approach to develop and implement a comprehensive,
multi-phase remedial action plan
for the Wing.
Instead of independently assessing each contaminated site,
DND is collectively considering all the sites to achieve
economies of scale, address cumulative affects (positive
and negative),
and optimize logistical considerations. The planned remediation
completion
date for this project is 2020.
This paper will present the
challenges faced by DND to manage, plan and execute a large-scale
remediation project
in a remote
area.
|
|
| Feasibility Testing and
Performance Monitoring of the Bioremediation of Contaminated
Sites in the Canadian Arctic
|
| more |
Charles W. Greer1, Danielle Beaumier1, Sylvie Sanschagrin1,
David Juck1, Serge Delisle1, Drew Craig2,
Don Kovanen2
1National Research Council, Biotechnology Research Institute
2Department of National Defence, CFB-Trenton
Polar soils are typically characterized as nutrient poor and limited
in available water. In the Canadian Arctic, the bioremediation
of hydrocarbon-contaminated soils is further complicated by the
low temperature, which has an impact on the bioavailability of
hydrocarbon substrates to bacteria and the activity of the degrading
bacteria in the soil. This study describes the initial bioremediation
feasibility testing and the subsequent on site treatment and monitoring
of diesel fuel contaminated soils originating from several fuel
spills at Canadian Forces Station (CFS)-Alert.
An initial laboratory
biotreatability study evaluated the presence of hydrocarbon degrading
viable bacterial populations, the genetic
potential of the indigenous soil bacteria to degrade fuel hydrocarbons,
and the degradation and mineralization activity of soils with
and without fertilizer amendments. The results demonstrated good
hydrocarbon
degradation activity by the indigenous microbial population following
nutrient amendment, and this activity was sustained at 4¾C. Chemical
analysis of the treated soil after three months of incubation
showed a reduction in residual hydrocarbons of 90% and 30% at 22
and 4¾C,
respectively. During the spring months an on-site biopile was
constructed in a bermed area at the station, and the contaminated
soil was
mixed with fertilizer and tilled into windrows ranging from 1-2
meters in height. Following a period of two months of on site
treatment, soil samples from the treatment area showed a considerable
increase
in the indigenous microbial population and in the hydrocarbon
degrading activity, resulting in a reduction of more than 60% of
residual
hydrocarbons. Soil samples taken after slightly more than one
year of on site treatment showed a reduction of more than 70% of
the
residual hydrocarbons and substantial increases in the numbers
of key bacterial genes involved in hydrocarbon degradation. These
results demonstrated that a simple treatment design that includes
controlled fertilizer amendment and soil tilling resulted in
an effective treatment for fuel hydrocarbon contaminated soil under
ambient climatic conditions at CFS-Alert.
|
|
|