|
Stream B: Remediation Case Studies
|
| Download Stream
B | PDF
| Back
to Stream Index
|
|
| Managing Uncertainty
by Planning for the Known Unknowns and the Unknown Unknowns Giant
Mine Remediation Project
|
| more |
Mark Cronk, P.Eng, Senior Project Manager, Giant Mine Remediation
Project, Public Works and Government Services Canada
In 1999, mine operations at Giant Mine in Canada’s Northwest
Territories ceased after 56 years of gold mining that established
the mine as the most prolific producer of gold in the Territories.
When the former owner, Royal Oak Mines, was forced into receivership
in 1999, Indian and Northern Affairs Canada (INAC) became actively
involved in the care and maintenance of the mine to protect human
health and safety as well as the environment.
The roasting process
used to the extract some seven million ounces of gold from refractory
Giant Mine ore yielded almost 237,000 tonnes
of by-product arsenic trioxide dust that was collected in a bag
house. This large volume of arsenic trioxide dust that is a highly
soluble and toxic form of arsenic is sealed in 14 underground
mine workings/chambers. On surface, numerous hazards exist, including
four separate tailings impoundments, a sludge pond, settling
pond
and associated dams. Most buildings on site are in an advanced
state of disrepair and will eventually be demolished. Risks associated
with a group of buildings known as the roaster complex are of
particular concern because these buildings are heavily contaminated
with arsenic
trioxide dust and loose fibrous asbestos. Around the mine site
arsenic, and hydrocarbon contaminated soils present additional
risks, as do numerous pits and underground openings throughout
the site.
In 2004, Public Works and Government Services Canada
(PWGSC) was retained by INAC as a service provider to oversee
management of
the Giant Mine site. This placed PWGSC in the awkward situation
where the organization had been charged with the responsibility
of maintaining one of the largest, most complex contaminated
sites in Canada, but using 60-year-old decrepit infrastructure.
In addition
to the surface infrastructure Giant has the added complexity
of requiring management of its underground infrastructure (mine)
to
allow for inspection, environmental compliance and future remediation
of the arsenic trioxide dust stored underground.
It was quite
a challenge for PWGSC, INAC and their team of experts to put
in place a contracting approach that could respond
quickly
and effectively to the broad range of unknowns they expected
to experience during five to seven years of care and maintenance,
not to mention unknown unknowns. In effect, the contract
stated, “do
what needs doing to keep the site in regulatory compliance” – you
figure out what that means. This required an innovative approach
to structuring government contracts that were flexible to
accommodate day-to-day care and maintenance of the site,
protection of
the environment and mitigating emerging risks that come with
managing
an abandoned 60 year old mining site. This innovative approach
established a balance of contract risks, between Canada and
the Contractor, for the continuing maintenance of this contaminated
site, until full remediation can commence.
This presentation
will speak to the challenges associated with maintaining
a 60-year old mine site using dated infrastructure,
how these challenges were overcome and give examples of
the types of obstacles that must be overcome routinely.
|
|
| Decommissioning of the
Sydney Steel Plant and the Redevelopment of the 180 Hectare Site
|
| more |
Gary Campbell, Nova Scotia Lands Inc.
Sydney Steel (Sysco) once generated 50% of all steel production
in Canada. Continued financial losses resulted in closure of the
plant in 2000. The provincial government established a $317 million
fund to decommission the plant, redevelop the site and provide
the Province’s share in the Sydney Tar Ponds Cleanup. Over
50 major buildings and other structures had to be demolished, along
with remediation of significant areas of contamination. One area
of the site required a 150,000 tonne ex-situ solidification project,
using a purposed built pug mill.
Decommissioning of the steel plant
is basically completed and extensive work is underway toward
redeveloping the site into a major commercial
park facility. Areas of the site are also being redeveloped to
support remediation activities of the adjacent Sydney Tar Ponds
and former Coke Ovens site. Further information can be found
at www.nslands.ca and www.tarpondscleanup.ca.
The presentation will
review the background of the steel plant site and the decommissioning/remediation
program for its redevelopment.
|
|
| Long-term Environmental
Project Management Strategy for North Warning System Short-Range
Radar Sites in the Arctic
|
| more |
Dr. Ken Reimer1,
Dr. Daniela Loock1,
Darren White1,
Kendra Leek1, Marten Devries1, Kim Kalen2, Al Cameron2
1Environmental Sciences Group, Royal Military College of Canada
2North Warning Systems Office, Department of National Defence
The North Warning System (NWS) is a collaboration between Canada
and the United States that provides aerospace surveillance over
the North American Arctic. Between 1986 and 1992, 47 unmanned short-
and long-range radar stations were constructed on Canadian soil.
In 1996, the North Warning Systems Office (NWSO) initiated a long-term
management program for the records of environmental conditions
of its short-range radar (SRR) stations. This program consists
of Phase II Environmental Site Assessments to assess operational
practices to date. Because of their continued relevance in Arctic
environments, the Distant Early Warning (DEW) Line Cleanup Criteria
for inorganic elements and polychlorinated biphenyls (PCBs) are
used as standards for identifying potential areas of concern. Petroleum
hydrocarbons are assessed based on the Indian and Northern Affairs
Canada (INAC) Protocol for the Remediation of Abandoned Military
Sites. Other contaminants of concern are assessed according to
the Canadian Council of Ministers of the Environment (CCME) guidelines.
These assessments will provide baseline environmental conditions
for each of the sites. As of the end of 2008, nine site assessments
had been completed by the Environmental Sciences Group (ESG) of
the Royal Military College of Canada. The completed survey and
assessment information become part of NWSO’s active geographic
information system (GIS). The GIS brings together all spatial and
aspatial data related to the sites. Data include analytical data
collected as part of assessment or remediation activities, site
drawings, surveys, photographs and other information generated
as part of the site operation. Managing these data in a central
repository facilitates effective identification and management
of common issues related to each reserve area, as well reducing
data collection related to the decommissioning of the sites in
the future.
|
|
| Giant Mine Remediation
Project: A Progressive Planning Approach
|
| more |
Martin Gavin, P.Eng, Manager, Giant Mine Remediation Project,
Indian and Northern Affairs Canada
In 1999, mine operations at Giant Mine in Canada’s Northwest
Territories ceased after 56 years of gold mining that established
the mine as the most prolific producer of gold in the Territories.
When the former owner, Royal Oak Mines, was forced into receivership
in 1999, Indian and Northern Affairs Canada (INAC) became actively
involved in the care and maintenance of the mine to protect human
health and safety as well as the environment.
The roasting process
used to the extract some seven million ounces of gold from refractory
Giant mine ore yielded almost 237,000 tonnes
of by-product arsenic trioxide dust that was collected in a bag
house. This large volume of arsenic trioxide dust that is a highly
soluble and toxic form of arsenic is sealed in 14 underground
mine workings/chambers. On surface, numerous hazards exist, including
four separate tailings impoundments, a sludge pond, settling
pond
and associated dams. Most buildings on site are in an advanced
state of disrepair and will eventually be demolished. Risks associated
with a group of buildings known as the roaster complex are of
particular concern because these buildings are heavily contaminated
with arsenic
trioxide dust and loose fibrous asbestos. Around the mine site
arsenic, and hydrocarbon contaminated soils present additional
risks, as do numerous pits and underground openings throughout
the site.
With the assistance of a Technical Advisors, INAC completed
a remediation plan for the site. During application for a water
license, the
remediation plan was referred to the MacKenzie Valley Environmental
Impact Review Board (MVEIRB) for an Environmental Assessment
(EA). As the EA progresses, the planning for implementation
of the project
continues, as does the care and maintenance of the site.
This
presentation will demonstrate the progressive approach to planning
during the life cycle of a major remediation project
that is contiguous from inception through close out. Focus
will
be on
the planning challenges to address the procurement, legal
and delivery issues and the strategies developed for these. The
presentation will also speak to the specific and dynamic
stages
on major remediation
projects such as pre-project planning, concept development,
regulatory approvals, numerous implementation stages, closeout(s)
and long
term monitoring and maintenance. Development of project delivery
structures to accommodate each stage will be discussed.
|
|
| Site Closure of an Outdoor
Firearms Range in a Municipal Watershed
|
| more |
Lisa Poier and Holly Herald, Royal Canadian Mounted Police
The Royal Canadian Mounted Police (RCMP) leased the use of property
under the jurisdiction of Metro Vancouver (formerly Greater Vancouver
Regional District) to operate an outdoor firearms training facility
(Firearms Range) from 1989 to 2006. The site was located within
the perimeter of the Coquitlam, BC, watershed, adjacent and upstream
of the confluence of Or Creek and the Coquitlam River, so environmental
protection was paramount throughout the site’s use and closure.
The RCMP Sustainable Development Unit devised and implemented an
approach for ongoing site maintenance throughout the operation
of the Firearms Range to manage the accumulation of spent munitions
in backstop berms behind targets and reduce sedimentation and erosion.
In 2004, the RCMP obtained the services of Keystone Environment
Ltd. to develop a site closure strategy for the site for the
Firearms Range that subsequently ceased operation in April, 2006.
Site closure
involved a series of detailed site investigations, habitat and
arbourist assessments, and communications with the landowner.
A combined physical remediation and risk assessment/risk management
strategy was determined to be the most appropriate solution for
addressing the metals contamination which had impacted the site
soils and sediments in the backstop berms, overshot areas behind
berms, range alleys where site users would stand during training,
and ditches and ephemeral waterways across the site.
Physical
remedial works were completed in the fall of 2007 and a Human
Health and Ecological Risk Assessment was conducted,
including a supplementary habitat assessment to confirm that
endangered species
were absent from the site and not using the site surroundings
as habitat. Results have confirmed that the physical remediation
was
successful and potential risks remaining at the site are sufficiently
low to meet the site management objectives.
Using this site
as a case study, the RCMP has developed alternate means for delivering
required Firearms Trainings, and is now
currently operating a partially-enclosed and contained outdoor
range with
a rubberized bullet trap system which allows for enhanced
environmental protection, capture and recycling of spent munitions.
Plans
are also being initiated to build a modern indoor firearms
range
facility, which will alleviate potential environmental risks
in the years
to come.
|
|
| A Collaborative and Integrative
Approach to the Assessment and Remediation of the Kingston Inner
Harbour and its Associated Properties
|
| more |
Kenneth J. Reimer, Viviane Paquin, Astrid Michels, Tamsin
Laing
Environmental Sciences Group, Royal Military College of Canada
Historical industrial activities have left a legacy of contaminated
sediments within the southwestern portion of the Kingston Inner
Harbour (KIH). The Environmental Sciences Group (ESG) of the Royal
Military College of Canada (RMC) has been conducting studies in
the KIH to determine the ecological impact of these legacy contaminants.
This research is being guided by the Cataraqui River Stakeholder
Group (CRSG) whose primary task is to identify an environmental
management strategy for the contaminated sediments. The CRSG members
are Parks Canada, Transport Canada, Environment Canada, Fisheries
and Oceans Canada, the Ontario Ministry of the Environment, Rideau
Renewal Inc., the City of Kingston, Canadian Forces Base Kingston
and ESG. The CRSG has adopted the Canada-Ontario Decision-Making
Framework for Assessment of Great Lakes Contaminated Sediment to
guide sediment management decisions for the KIH. The research program
developed by ESG addresses all of the scientific questions considered
in the framework, so that a definitive management decision can
be made. A preliminary delineation of the area in which contamination
is having adverse ecological impacts, and where management actions
will likely be required, has been performed. The group must now
come to a consensus on the design of a remediation approach and
what supplemental studies are needed, if any, to further refine
the area requiring management action. This presentation will describe
ESG’s role in facilitating a collaborative approach to the
assessment and remediation process, and the benefits of such collaboration
when multiple stakeholders share responsibility for a site and
where the investigation and cleanup of adjacent properties must
be integrated into the overall assessment and remediation approach.
|
|
| Contaminated Site Management
Contributes to Maintaining and Improving Ecological Integrity
in Canada’s National Parks
|
| more |
Mikaïlou Sy, Kathie Adare, Jean-Claude Prévost
Parks Canada Agency
With respect to the management of protected areas, Ecological
Integrity (EI) refers to a condition characteristic of the respective
natural region which likely persists in its biotic and abiotic
components, and interactions therein, as well as in its overall
functionality, including the supporting processes and their rates
of change. Protected areas, such as National Parks, which maintain
and improve their EI, often exhibit both a strong resistance to
stress and a high resilience following disturbance, and are therefore
valuable management tools for resource conservation. However, perturbations
such as contamination, more often than not, from pre-park establishment
may disrupt EI equilibrium and pose long-term environmental and
human health risks, if not properly managed. Along with sound environmental
stewardship, the assessment and remediation or risk management
of contaminated sites in National Parks may thus contribute to
maintaining or restoring healthier ecosystems. This paper will
summarize key environmental risks posed by 20 contaminated sites
from 20 National Parks throughout the Parks Canada network, highlighting
the exposure pathways and receptors at risk along with risk mitigation
measures in place. This review will further demonstrate how the
ongoing assessment, remediation and risk management activities
contribute to maintaining and improving EI in Canada’s National
Parks, and help provide quality visitor experience while promoting
sound environmental stewardship.
|
|
The Port Hope Area Initiative:
Application of Project Management Tools to
Contaminated Site Remediation Projects
|
| more |
Tim Palmeter, Public Works and Government Services Canada
Marcia Blanchette, Natural Resources Canada
Glenn Case, Atomic Energy of Canada Limited
This presentation is intended to demonstrate the importance of
applying project management tools and processes to contaminated
site remediation projects.
The management of projects is key to
providing value for money and demonstrating sound stewardship
in program delivery. A comprehensive
approach to managing projects, which is integrated across the
department and is appropriate for the level of risk and complexity,
will enhance
the likelihood of realizing project outcomes.
The Port Hope Area
Initiative (PHAI) is a community-based program directed at the
development and implementation of a safe, local
long-term management solution for an estimated two million
cubic metres of historic low-level radioactive waste (LLRW) in
the
Port Hope, Ontario area. Since 2001 the PHAI has undergone
extensive public consultation, environmental assessment and licensing
review
of proposed solutions for the safe, long-term management of
LLRW in the Port Hope area. The PHAI is now entering a transition
phase
with a key objective of establishing an appropriate governance
and procurement framework for project delivery.
The PHAI project
consists of:
-
Remediation
of some 17 major sites and an estimated 400 minor sites with
a total contaminated soil volume of 575,000 cubic
metres;
- The remediation of two existing
radioactive waste management facilities with a total contaminated
soil volume of 950,000 cubic metres;
- Remediation of five industrial
sites with a total contaminated soil volume of 50,000 cubic metres;
and,
- Construction of two engineered above ground facilities for the
long-term waste management facilities with a combined capacity
of 2.5 million cubic metres.
Natural Resources Canada (NRCan), Atomic
Energy of Canada Limited (AECL) and Public Works and Government
Services Canada (PWGSC)
have committed to deliver this project in a manner that reflects
the federal accountability framework, industry best practices,
with appropriate project management, risk management and
quality assurance considerations.
NRCan, as the project sponsor,
has overall responsibility for
all aspects of the PHAI. AECL, as the delegated project
proponent and
as the licensee, is responsible for overall conduct of
the project. PWGSC, as the main contract arm of the Government
of Canada,
is responsible for managing the major contracts and acquisition
activities
associated with the project.
Utilizing project management
(PM) tools and processes, such as project charters, and work
breakdown structures,
is an essential
component of managing complex, multi-stakeholder projects
such as the PHAI. Strategic implementation of PM tools
helps to build
an awareness of the broader project context for the project
team members, and allows for a better integration of
specific project
objectives and strategies.
|
|
| Challenges in Barrier
Wall Construction and Site Remediation on Esquimalt Harbour:
Remediation of the Yarrows Shipyard, CFB Esquimalt
|
| more |
Jeff Nyman, SLR Consulting
Duane Freeman, CFB Esquimalt, Department of National Defence
Andrew Smith, Public Works and Government Services Canada
The remediation of the former Yarrows Shipyard, property acquired
by Department of National Defence (DND) in 1996, utilized innovative
remediation technologies to remediate the site. The remediation
was both technically challenging due to site conditions, as well
as due to location: an active military-industrial harbour, with
prominent First Nations, recreational, and economic components.
In September 2008, DND undertook remediation of the former Yarrows
Ltd. Shipyards, property acquired by DND in 1996 in lieu of taxes
and known environmental liabilities. The acquisition of the property,
with estimated environmental liabilities (soil) of $1-2 Million
(1995 estimate), represented a “once-in-a-lifetime” opportunity
to join Naden, the administrative area of CFB Esquimalt, with
HMC Dockyard, the operational home of Canada’s Pacific
Naval Fleet, gaining valuable waterfront property with access
to deep
water, while reducing travel time and security costs between
the two areas.
The site has a long and varied history, with military
and industrial
presence pre-dating the Confederation of Canada in 1867, and
a First Nations presence likely pre-dating Jesus Christ. Shipbuilding
and repair activities became significant in the 1890’s.
In 1924, a large area of Lang Cove was in-filled to create
site boundaries.
The choice of fill materials included boulders, concrete, bricks,
clinker, slag, lead shavings, sheet metal, pipes, and creosoted
timbers.
When DND acquired the site, most infrastructure had
been removed or buried, and the site was capped with gravel
to make a laydown
area. In 2000, DND removed known contaminated surface soils
and placed them in an engineered waste storage cell and then
later
disposed of them off-site in permitted landfills. Monitoring
wells were installed and the site was monitored as part of
the risk management
strategy.
In 2005, free-product was detected in two monitoring
wells at opposite ends of the site. The risk management strategy
was reviewed,
additional
investigation was undertaken, and expert support was provided
by Fisheries and Oceans Canada and Health Canada as part
of the Federal
Contaminated Sites Action Plan to determine the best approach
to manage the site. This work resulted in the site being
classified as a Class I Contaminated Site, requiring remediation.
A remediation plan was developed in 2007, but due to the heterogeneous
site fill, DND, working with Public Works
and Government Services,
did not wish to prescribe what kind of method to employ
to allow for deep excavation of the foreshore, only what
objectives
needed
to be met. This was done to minimize DND liability and
maximize contractor innovation and competitiveness.
The
remediation, undertaken in September 2008, involved installation
of 3,200 m2 of
barrier wall, utilizing bentonite slurry and
drilled caissons, to depths of –14 m, footed
in either 3’ of native
clay or resting on bedrock. This allowed for bulk excavation
to bedrock of 60,000 m3 of
contaminated soil, within two metres of
Esquimalt Harbour. The installation was significantly
challenging with many lessons learned, as was the excavation
of contaminated
soil itself. Numerous underground storage tanks were
found at great depth containing free product, which
greatly increased the scope
and magnitude of soil contamination found at the site.
|
|
|